27,600m3

VENM EXCAVATED

94,000t

SELECT FILL PLACED

11,800m2

LINER SYSTEM INSTALLED

Client Richmond Valley Council
Location Nammoona | NSW
Value $4.2m
Timeline Jan 2023 - Dec 2023

Synergy was contracted by Richmond Valley Council to construct the new Landfill Cell 6A completed with an integrated Sedimentation Basin and Leachate Pond. Excavation and construction were undertaken using GPS machine control with the works completed to level 1 Geotechnical supervision in accordance with EPA guidelines for modern solid waste Landfills.

Cell 6A is the first stage of a major solid waste Landfill expansion for Richmond Valley Council that will stop the transport of the area’s solid waste to Queensland and create a revenue stream for the community. The project comprised the construction of a 9,750m2 landfill cell, the construction of a Sedimentation Pond to capture diverted stormwater from the area and a lined Leachate Basin to capture and store leachate from the Landfill.