Spanning a 1.8km cross-section, bridging two towns via a sporting and nature complex, this was an all-encompassing civil and environmental development to create international-standard sporting facilities including Rugby, AFL / Cricket, Tennis and Netball playing surfaces, with sealed access / parking, lighting and electrical, sewer, water reticulation, storm water management infrastructure, plus 57,500 native plantings.
Quality community engagement was essential to the success of the project. A council reserve was being used as extended backyards and project infrastructure included this reserve. Transparent and open engagement with residents fostered good will, enabling the project to be completed in 20 months, within budget, and approximately 20% less than the optimum specification required. Our safety record was outstanding, with only one lost worker day due to a minor injury. Our client was very satisfied, and is championing us throughout the region.